Wednesday night, Kentucky Transportation Cabinet contract crews will close I-65 South to reinstall the truss and signs knocked down at the Exit 91 approach back in March of this year.
The work schedule is as follows:
1.) 9:00pm / right lane closure
2.) 10:00pm - 10:15pm / rolling road block traveling S/B to set the truss upright on the left shoulder
3) 11:00pm - 11:15/ rolling road block to set the truss over the interstate
*** Lane Closure Should be picked up and traffic back to full flow on the southbound side of the interstate by 12:00 or 12:30am.